Projects Ongoing Details



Construction of North Bengal Tea Park

Sources of Fund

Grand from ASIDE – 1600 Lac , S.J.D.A Contribution – 792 Lac.

Estimated Amt. : Rs 2392 lac

PROJECT PROFILE: - Tea Park is being developed by SJDA in 50 acre area near NJP Railway station in collaboration with Tea Board. It has been conceptualized for the Tea Industry keeping in mind the comparative advantage of quality tea growing the state enjoys. This park is being planned to be set up for integration of tea production and tea processing facilities based on the industry cluster concept where the industries would have the provision of support facilities. The park would have (CTC and Orthodox) tea production units for small tea gardens which do not have their own facilities, tea blending units, flavored tea production units, scientific warehouses, etc. Thus it will make tea production more cost effective which would increase the competitiveness of Indian tea. At present basic infrastructural development comprising Boundary Walls, Land Development, Internal Roads and Approach Roads, Toilet Block and Surface Drain works are completed and, Administrative building etc are going on and 60 % of total works are completed so far.

Physical Progress : 80%

Financial Progress : 60 %


Construction of Bridge over River Buri Balason Including Both Sides Apporoach

Sources of Fund

Plan Grant: 11-12 Rs. 117.52lac

Plan Grant: 12-13 Rs. 112.48 lac

MPLAD: Rs. 30.00 lac

Estimated Amt.: Rs. 260 Lac

PROJECT PROFILE :- This major Bridge project had been taken up by S.J.D.A. .which consist of 4( four) nos. of Span each 17.5 meter long .having total length of 70 meter (excluding both side approaches) and 6.0 meter wide carriageway with 1.20 meter wide footpath on both sides. Provision has been made in this project with R.C.C Bored Pile Foundation with R.C Girders Superstructure. The total cost of Rs. 260 lac has been considered for execution of this project.

The physical execution of this work was started from the month of November 2010 and at present foundation and sub-structural works are completed and super structural works is going on in bridge proper

Physical Progress : 35 %

Financial Progress : 27 %


Construction of Bridge over River Karala at Samajpara, Jalpaiguri

Sources of Fund:

Plan Grant: 10-11 Rs. 0.47 lac

Plan Grant: 11-12 Rs. 104.18 lac

Plan Grant: 12-13 Rs. 55.35 lac

Estimated Amt.: Rs. 160 lac

PROJECT PROFILE :- This major Bridge project had been taken up by S.J.D.A. .which consist of 3( three) nos. of Span 2 nos of 12.5 meter long and 1 no of 18 m long .having total length of 43meter (excluding both side approaches) and 5.5 meter wide carriageway with 1.50 meter wide footpath on both sides. Provision has been made in this project with R.C.C Bored Pile Foundation with Built up section steel girder and R.C C. Deck slab Superstructure. The total cost of Rs. 160 lac has been considered for execution of this project.

The physical execution of this work was started from the month of January 2011 and at present foundation and sub-structural works in bridge proper are completed and superstructure work is going on.

Physical Progress : 40%

Financial Progress : 20 %


Construction of Land Custom Station at Fulbari

Sources of Fund

Grand from ASIDE - Rs.1215.5 Lac

S.J.D.A Contribution - Rs.187.5 Lac.

Estimated Amt. : Rs 1403 lac

PROJECT PROFILE: - Infrastructure development of Land Customs Stations (LCSs) is important for proper and smooth exporting of perishable as well as non-perishable commodities to neighbouring countries - Bangladesh, Nepal, Bhutan etc. Development of the infrastructure in different LCSs have been approved both under Critical Infrastructure Balance Scheme (CIBS) and now under Assistance to States for Infrastructure Development of Exports scheme (ASIDES). Through the LCSs a big boost of India's trade wilhperform with neighbouring countries. The LCSs are primarily gateways for transit of goods, services and human beings between the neighbouring countries.

Siliguri Jalpaiguri Development Authority (SJDA) has been taken a thrust project on development of LCS at Fulbari, Siligun along with a truck terminal for boosting up exports to neighbouring country Bangladesh through nearing Fulbari border.

Physical Progress : 90%

Financial Progress : 80 %


Construction of Library Building at Himanchalvihar, Matigara, Siliguri

.

Sources of Fund :

Mass Education Extension and Library Service Department: Rs.163.25 Lac.

S.J.D.A Contribution - Rs.10.43 Lac.

Estimated Amt: Rs. 173.68 lac

PROJECT PROFILE:- Mass Education Extension and Library Service Department, Government of West Bengal in association with Siiiguri Jalpaiguri Development Authority has taken up this project for construction of a new Library Building at Himachal Vihar, Matigara, Siiiguri. S.J.D.A has allotted 7.26 katta of developed land free of cost ( cost of land Rs. 10.43 lakh ) Administrative approval and financial sanction of Rs. 163.25 lakh has been accorded by the Finance Department and Mass Education Extension and Library Service Department to Siiiguri Jalpaiguri Development Authority for construction of this building (four storied ) . Once functional, this will assist for development of human resources in North Bengal.

Physical Progress : 75 %

Financial Progress : 50%


Construction of RCC bridge over River Mahananda near Ramghat. Siliguri

Sources of Fund:

Plan Grant: 11-12 Rs. 197.60 lac

Plan Grant: 12-13 Rs. 352.40 lac

Plan Grant: 13-14 Rs. 300.00 lac

Estimated Amt: Rs. 850 lac

PROJECT PROFILE :- Vast area of Matigara though situated very close to the BURDWAN ROAD and core area of Siiiguri town but completely isolated due to natural barrier of river Mahananda. To ensure uniform development particularly on peri-urban areas of Siiiguri town and to build up direct and uninterrupted connectivity from Burdwan road to National Highway, NH-31 through Matigara, SJDA has taken up this project for construction of important Bridge over river Mahananda connecting to S.F road of Siiiguri at one end and NH-31 through Matigara on other end.

After construction of this major Bridge over river Mahananda vast area of Matigara will be directly connected to core area of Siiiguri town through S.F. road resulting uniform development and socio-economic growth of this area and more than 100,000 people will be directly benefited from this project. The physical execution of this work was started from the month of April 2011 and at present foundation work is completed and sub-structural works in bridge is going on.

Physical Progress : 15 %

Financial Progress : 8%