SJDA has submitted the Detailed Project Report (DPR) to NRCD for
approval from Govt. of India on March 2004. The project has been
approved technically and now placed to Economics Finance Committee
for final approval. The project has been approved as 70:30 cost
sharing basis between Central Govt. and State Govt., WB. The total
project cost is Rs.38.04 crores in Phase-I, consisting the following
project components:
- Interception of Diversion Sewage System for Mahananda, Fuleshwari
and Jorapani rivers.
- Three (3) no. Sewage Treatment Plant (STP) for Mahananda, Fuleshwari
and Jorapani river.
- River Front Development of Mahananda River.
- Soil Conversation programme including afforestation.
- Provision of Bathing Ghats along with bank protection.
|