Year |
Month |
Events |
Photographs |
|
1980 |
APR |
SJDA formed in 1.4.80. Sri B C Ghosh took over as Chairman (1.4.1980
– 29.8.1983) |
|
|
JUL |
Land Use Survey started |
|
|
1983 |
AUG |
Prof. Dipti Bhusan Dutta took over as Chairman (30.8.83 — 29.8.86) |
|
|
1986 |
AUG |
Sri Swapan Sarkar took over as Chairman (30.8.86 - 29.8.87) |
|
|
DEC |
Submission of ODP |
|
|
1986 |
AUG |
Sri Balbir Ram, IAS, appointed as Development Authority in respect
of planning area (30.8.87 – 28.5.90) |
|
|
1990 |
MAY |
Smt Kalyani Choudhuri, IAS, Divisional Commissioner, Jalpaiguri
Division, took over as Chairman (29.5.90 — 31.7.91) |
|
|
1991 |
JAN |
Draft ODP approved under section 36(1) of the T&CP Act. |
|
|
MAR |
Electric Crematorium at Siliguri: Located by the side of
Mahananda River near Mahananda Bridge, helps to reduce pollution
level and wood usage. Project completed in March 1991. Cost Rs 74
Lac |
 |
|
APR |
Market cum Office Complex at Dinbazar, Jalpaiguri: Located in
the core area of the city to provide modern shopping and office
facilities. Project Cost Rs 98 lac |
 |
|
MAY |
Bus stand and D.I. Fund Market at Naxalbari: To provide bus
stand facilities and market facilities in that area. Project Cost Rs
52 Lac |
|
|
JUN |
Bridge over river Rook Rooka at Jalpaiguri: Links Jalpaiguri
Engg. College to Jalpaiguri Polytechnic. Project Cost Rs 13.87 lac |
 |
|
AUG |
Sri Asok Bhattacharya, Minister-Of-State, Municipal Affairs
Department took over as Chairman (1.8.91 – 26.03.96) |
|
|
SEP |
Improvement of Karbala Maidan:
Project Cost Rs 10.54 lac |
 |
|
Tenzing Norgay Central Bus Terminus at Siliguri: Located near
Siliguri Railway Junction to give terminal facilities to Govt. and
private buses. Project Cost Rs 191 Lac |
 |
|
1992 |
MAR |
Public notice inviting objections on ODP Published on 1.4.1992 in
newspapers |
|
|
JUN |
Approval of ODP in 54th meeting held on 22.6.1992 for submission to
State Govt |
|
|
JUL |
Request for final approval of ODP under section 37 of T&CP Act sent
to Govt. |
|
|
AUG |
Govt. approval of ODP under section 37 of T&CP Act received.
|
|
|
NOV |
SJDA Market And Office Complex: Built to provide resettlement
of hawkers in bus terminus area, to create shopping facilities for
the transit passengers and to provide office facilities for RPFC and
SJDA. Project Cost Rs 120 lac |
 |
|
DEC |
Gazette notification published on 22.12.1992 notifying approval of
O.D.P |
|
|
MAY |
Decision of SJDA in its 58th meeting on 22.5.93 for imposition of
development charges as per chapter IX of WBT & C(P&D) Act,1975 |
|
|
JUL |
Proposal sent to UD Dept for approval of Development charges
|
|
|
1994 |
MAR |
Second Mahananda Bridge: To avoid bottlenecks of traffic flow
a second bridge over Mahananda has been constructed. PWD (North
Bengal Construction Division) has executed the work. Project Cost
377 lac |
|
|
OCT |
Approval of State Govt.received under section 102 of WBT&C(P&D)
Act,1975 to impose development charges |
|
|
Next >> |